Operation department owns this tab: prepare the stock, transfer it from inventory, and when the MO is ready for the workshop push it to IN PROGRESS. BLOCKED = quick fix — do what the note asks, then unblock · PAUSED = heavy problem (most items unavailable, takes time) — parked as "partially completed" in Katana for the fixing team · AWAITING = not started, lines being gathered / verified. Note format: BLOCKED: reason | NEED: item | BY: date | WHO: sales/purchase
Production plan: deadline first, then each day is filled close to capacity with the next orders in line (±200 pcs). A bulk order bigger than one day leads its days with ~66% of capacity — the rest goes to the next orders so every client keeps moving. Workflow order on multi-service orders (1-day lag between stages): coloring → printing → filling (needs mixing + printing + coloring done) → sticker application → packing → cellophane. ● WORKING = started · ○ TODAY = planned for Day 1 · ○ TO DO = Day 2 onwards or waiting for an earlier service.
Workshop
Completed Quantity — Last 14 Days
units finished per day · click any day for its exact orders
Workload by Section
click a section to open its services — plan manpower by where the queue is heaviest
Section / ServiceIn QueueAwaiting BlockedPausedDone (7d)Capacity/day≈ Days to clear
≈ Days to clear = in-queue quantity ÷ max daily capacity, orders taken in deadline order. A section's figure is its slowest service (the bottleneck) — red needs manpower.